Approving adjustment of investment policy and the investor for Huong Linh 3 WPP – Chairman of Quang Tri Provincial People’s Committee (PPC) Vo Van Hung has just signed Decision No. 756/QD-UBND approving the adjustment of investment policy and the investor of the Huong Linh 3 wind power project. According to the Decision, the investment policy of Huong Linh 3 Wind Power Project is the first time approved by Quang Tri PPC for the Huong Linh 3 Wind Power Joint Stock Company (headquartered in Cooc village, Huong Linh commune, Huong Hoa district) as the investor (Decision No. 781/QD-UBND dated April 9, 2019). The Huong Linh 3 wind power project with a total capacity of 30 MW, average generation of 123.329 GWh/year is designed with 9 wind turbines with each capacity from 3.3 to 3.465 MW. The project is implemented on 8 ha in Huong Linh commune, Huong Hoa district (excluding land area for the foundations of the connecting grid to the national power system). The total project investment capital is more than 1,530 billion VND. According to the project progress in the decision on approving the investment policy, from March 2019 to May 2019, establishing technical design, construction drawing. In December 2020, […]
PVN and US partners held discussions on the cooperation in investment in offshore wind power and hydrogen projects – On March 2, 2022, in Hanoi, Mr. Hoang Quoc Vuong, the Chairman of the Member Council of Vietnam Oil and Gas Group (PVN) and Mr. Mark Green – Chairman of the Asia-Europe region of AES Corporation (USA) discussed cooperation in developing offshore wind power and hydrogen projects in Vietnam. At the meeting, Mr. Mark Green updated on the implementation status of the Son My LNG Terminal project: after establishing the Charter of Son My LNG Warehouse Company, the agreement and necessary documents suitable with Vietnamese laws for founding Son My LNG Warehouse Company were signed by PV Gas and AES on February 27, 2022, the documents on Son My LNG Warehouse Joint Stock Company ware submitted to Binh Thuan Provincial Department of Planning and Investment. At present, the sides are actively coordinating to work with Binh Thuan provincial relevant agencies to as soon as possible obtain the Investment Registration Certificate and finalize relevant investment procedures. Mr. Hoang Quoc Vuong considers Son My LNG terminal is an important project for Vietnam and PVN wishes to promote the project implementation towards synchronizing the use of LNG for power […]
Ørsted and T&T Group hold first supplier event for their multi-GW Offshore Wind pipeline in Vietnam – The event, held on Thursday, 20th of January, was co-hosted by representatives from MOIT, MPI, and the Danish Embassy, and is the first of many initiatives that will be undertaken by Ørsted and the T&T Group to help local companies become suppliers to the industry and the partnership’s multi-GW pipeline of offshore wind projects. From left: James Won – Head of CS Wind Vietnam, Sebastian Hald Buhl – Vietnam Country Manager, Pascal Langeais – Ørsted Head of APAC Procurement & Supply Chain, Troels Jakobsen – Head of Commercial Section, Danish Embassy, Le Tuan Anh – Director of Economic Industry Dept of MPI, Sivert Skarn – General Director Vard Vung Tau, Pham Nguyen Hung – Deputy General Director of EREA/MOIT, Nguyen Thi Thanh Binh – Vice General Director T&T Group. The well attended workshop saw presentations from Ørsted’s supply chain experts and speeches by representatives from the Economic Industry Department under the Ministry of Industry and Trade and the Electricity and Renewable Energy Agency under the Ministry of Industry and Trade. It was noted that Vietnam’s national energy development strategy gives a clear mandate […]
Inaugurating Dong Hai 1 Wind Power Project – On January 16, 2022, Trungnam Tra Vinh 1 Wind Power Joint Stock Company, a member of Trung Nam Group held a ceremony for inaugurating Dong Hai 1 Wind Power Project in Tra Vinh province. This project is the first step for the “sea voyage” demonstrating the construction capacity of Trungnam Group, in successful implementing the first offshore wind power project, overcoming the trial of the time and natural unfavorable factors in the Southwest region, opening the way for offshore wind power projects of Trung Nam Group in coming time. Dong Hai 1 Off-shore Wind Power Project (OWPP) is developed in Duyen Hai district, Tra Vinh province with a capacity of 100 MW, average generation of 330 GWh/year. The project invested by Trung Nam Tra Vinh 1 company with a total investment of 5,000 billion VND. The project includes 25 wind towers at the sea positions V1-7. Dong Hai 1 Wind Power Project in Tra Vinh province. During the construction process of nearly 10 months, Trungnam Group transported nearly 70,000 tons of equipment and materials over a distance of more than 12,000 km to gather at the project. More than 1,100 engineers and workers […]
GOLDWIND and BIDV establish a cooperative relationship 09:57 | 21/12/2021 – On November 17, 2021, Goldwind International Vietnam Co., Ltd signed a Memorandum of Understanding (MOU) with BIDV (Bank for Investment and Development of Vietnam). Accordingly, Goldwind and BIDV will cooperate together to support owners of wind power projects. In which, Goldwind- the second turbine OEM supplier of the world will manufacture and provide turbines, O&M service. Additionally, BIDV- top banks of Vietnam will support and provide credit and financial services for the wind projects Attending the signing ceremony, there are Mr. Tran Long – Deputy General Director of BIDV, Mr. Wang Hai – Deputy General Director of Goldwind – the owner of Goldwind International Vietnam Co., Ltd. The signing ceremony of the MOU between Goldwind and BIDV is really an important milestone in the journey of building a cooperative relationship between the two entities. Goldwind is the world’s leading provider of renewable energy solutions. Since its establishment, Goldwind has always taken “Innovating for a brighter tomorrow” as its mission. The wind power industry is a long-distance race that tests endurance. Only through advanced technology, high-quality product quality and reliable service as a practical guarantee can Goldwind create true value for customers and […]
GW165/4.0MW won the “2021 Best Turbine Technology of the Year” award from Lead Energy ASEAN Wind Energy – Leader Associates is the world’s leading organizer of renewable energy activities. It has a greater reputation and influence in the ASEAN region, East Asia and Australia. Goldwind is honored to receive -“2021 Best Turbine Technology of Year” for Goldwind turbine: GW165/4.0MW”. Goldwind began to explore the Thai market since 2012, with GW121/2.5MW WTG 120m soft tower. After the success in the Thai Market, Goldwind’s exploration footprint in ASEAN countries began. In 2018, according to the wind resources and development conditions of 6.5-7.5m/s equal or below class III in Southern China and the central-South and southern coastal areas of ASEAN countries, GW165-4.0 products were developed, together with steel/ hybrid tower solutions, 160m and above. In order to further optimize the LCOE of the wind farm owner, and replace the traditional “cost thinking” with “income thinking”. Award “Best Turbine Technology 2021” for Goldwind’s GW 165/4.0 MW turbine. The GW165/4.0MW owns many advantages: Permanent magnet direct drive products have 4 major features, few components, easy maintenance, no coupling, no gearbox, on the one hand, it helps to achieve a significant improvement in cost efficiency and engineering efficiency. At the […]
Our Story In 2012-2014, Son Ha Mechanization Construction & Transport JSC started serving projects such as: Mong Duong 1, 2 thermal power plants, Nhat Tan Bridge, Terminal T2 at Noi Bai airport, maintenance of Ca Mau. 2014 – 2015: Opened PRC projects services invest Company (later renamed Son Ha company), we participated in the key project Nghi Son Refinery and Petrochemical – Thanh Hoa, Formosa steel factory & port complete – Ha Tinh. Son Ha invested in buying the first 120 ton crawler crane. For rental crawler crane Liebherr LR1550, 550 ton biggest in Formosa project Heavy lifting services contract 550 ton crawler crane for Messer Hai Duong gases factory 2016-2018: We have a huge development in big projects and overseas projects First project in Cambodia – Heavy lift services for Heineken factory First Project Marine works – Piling works for DKC class Oil Tanker Berthing Facilities project – First in Vietnam use Jackup barge for construction. Heavy lift services use crawler crane 600 ton CC2800-1 and 250 ton Kobelco 7250-2F 2018-2021: This period is the development of wind power projects, with the advantage of experience in heavy lift and marine construction. We continue to execute large projects wind power projects […]
Agreeing on the policy to invest in a wind power equipment manufactory in Nam Dinh – Information from Nam Dinh provincial People’s Committee (PPC) said that PPC of this province has just agreed to the policy for Rang Dong Mechanical Joint Stock Company (under Xuan Thien Group) to research and survey the off-shore wind power projects on the sea of Giao Thuy, Hai Hau and Nghia Hung districts, and built a wind power equipment manufactory in Nghia Hung district. In October the Xuan Thien group proposed to invest in Rang Dong Mechanical Manufactory in Nghia Hung district for manufacturing wind power turbines and towers with a total capacity of 1,000 MW per year, including an off-shore turbine with a capacity of 5-20 MW on each tower. Rang Dong Manufactory places a goal to reach a localization rate of 70% for every wind power turbine. Rang Dong Manufactory will also manufacture the heavy industrial mechanical equipment Rang Dong Mechanical Manufactory with a total investment level of 3,000 billion VND expects to be started in May 2022 and completed in 2024. Along with agreeing on investment policy on building Rang Dong Manufactory in document No 913/UBND-VP5 dated November 22, 2021 Nam Dinh PPC […]
OCCUPATIONAL HEALTH AND SAFETY (HSE) AND ENVIRONMENTAL POLICY Our commitment is to continuously improve our environmental performance and make sustainable contributions to our operations and society. SON HA MS bases its activities on the life cycle, circular economy, sustainable development and continuous improvement principles. OUR GOAL Complying with all legal requirements related to occupational health and safety (HSE) and environmental issues and improving them by making them a part of the company culture. Taking all preventive measures by identifying the dangers related to ohs in the organization with a systematic approach before the accident and occupational diseases occur. Raising the awareness of our employees on creating a healthy and safe working environment is our primary goal and organizing the necessary training activities within this cntext. Presenting our customer energy solutions in the most beneficial and environmentally conscious manner, Developing environment friendly products and services. Providing unconditional and willing compliance with environmental and ohs regulations. Spreading its environment friendly perspective by raising the awareness about the environment with employees and customers, Considering environmental impacts strictly in all our business processes related to our subject, Ensuring that works are carried out to prevent any kind of environmental pollution that may occur […]
Hoa Binh 1,2 (2 phase) wind farm project. Location: Hoa Binh, Bac Lieu Province, Viet NamScope of work: Piling works PHC D800/60-70m (From March/2020 to October/2020) Total: 15,000mdEquipment’s Used: Barge/crane: 3600 tons/200 ton, diesel hammer 10 ton… Barge/crane: 9000 tons/250 ton, diesel hammer 10 ton… Barge/crane: 1800 tons/150 ton, diesel hammer 10 ton…
With extensive experience in heavy machinery solutions and experience in construction in many different sea areas from the North to the South and Phu Quoc Island, we provide solutions for construction of offshore projects: – Offshore power line poles – Wind power foundations – Marine berth and piers – Seaport wharf bridges – Submarine cable laying
With many years of experience in constructing various projects, we are currently working with close partners to provide the best solutions for building BOP packages for nearshore wind power projects to customers: – Foundation design: Top 1 the world – Foundation Reinforcement > 100 WTGs – Marine supply concrete > 100 WTGs – Piling works > 70 WTGs – Facilities International port > 150 WTGs – Wind marine Transportation > 150 WTGs – Lifting & Installation wind turbines > 100 WTGs – Submarine cable construction > 3 Projects similar
Son Ha provides solution for new-build construction, operations, maintenance, and decommissioning projects. Our extensive offering covers a diverse range of industrial facilities, including wind turbines onshore and offshore structures. We serve clients in the sectors of wind renewable energy. Through careful planning, coordination, and collaboration, we tailor our services to your unique parameters and objectives. From BOP seaworks to turnkey engineering, procurement, and construction (EPC), each job we undertake integrates design, project management, and technical support services. With safety as the utmost goal, our specialists focus on providing efficient heavy lift solutions—from factory to foundation. Our qualified personnel bring real-world experience and specialized training to each job site, leveraging only the most up-to-date technologies and equipment available. Advanced 3D Lift Plan Software Technology Unforeseen complications can quickly threaten any project’s budget, timeline, and overall success. Implementing an initial planning process is crucial to identify, mitigate, and circumvent challenges as early as possible. To ensure success and safety, Son Ha Companies professionals utilize 3D Lift Plan software. Using this advanced 3D lift planning and crane selection application, we produce highly accurate drawings that enable the entire team to visualize the project, from the earliest stages to final handover. Our lift plans […]
At Son Ha, we have the noble mission to be the professional in wind onshore construction and wind nearshore construction, heavy lifting, and BOP package for our clients. To do this, We are committed to making every effort to find improved technology, solutions, products and services to meet the growing needs of our customers. Click our Son Ha Code of Conduct document to get an insight on the integrity with which we work at Son Ha.
VPL Ben Tre offshore wind farm Location: Thoi Thuan, Binh Dai dist, Ben Tre Province, Viet NamScope of work: Piling works PHC D800/60-70m (from March/2021 to May/2021) total: 15,000mdEquipment’s Used:1. Barge/crane: 3600 tons (71×18.5m)/200 ton, diesel hammer 10 ton… Barge/crane: 9000 tons(100×27.5m)/250 ton, diesel hammer 10 ton… Barge/crane: 1800 tons(52x16m)/150 ton, diesel hammer 10 ton… Barge/crane: 3500 tons(63x20m)/250 ton, diesel hammer 10 ton… Barge/crane: 5400 tons(73×24.5m)/150 ton, diesel hammer 10 ton…
Ben Tre Renewable Energy JSC has been granted to invest more than 4,000 Billion VND into Ben Tre V1.3 Offshore Wind Farm. This project is an offshore wind farm with 110MW capacity, which is located in Ba Tri Commune, Ben Tre Province, Viet Nam. The operation of the wind farm not only helps the Government achieve the country’s wind energy capacity to 2000MW by 2025 but also supports Vietnam’s transition to a low carbon energy system. SIGMA Engineering JSC, for the first integration into the renewable energy field, has demonstrated its capabilities and has won the engineering, procurement, construction (EPC) contract for the Phase 1 of Ben Tre V1.3 Offshore Wind Farm. This phase has encompassed 07 offshore wind turbines with the total capacity of 30MW, which is connected to the 110 KV substation along 15km of Submarine 22KV cable system and entering the national power grid with more than 11Km of 110KV transmission line. The first phase project is expected to begin commercial operations in the first half of 202
Location: Kien Giang offshore, Kien Giang Province, Viet Nam Scope of work: Piling works PHC D700 & D800 Equipment’s Used: Barge 1800 tons & 1000 tons, crawler crane 150 tons – IHI CCH1500E, diesel hammer 8 ton… The 220 kV Kien Binh – Phu Quoc transmission line, one of the national key projects to strengthen the electricity supply for Phu Quoc city (Kien Giang province).The project with a total length of 64.7 km and investment of 2,212 billion VND. This is the first 220 kV transmission line across the sea in Vietnam. The project is double line with two conductors by section of 2xAC400 in a phase placed on the 117 towers. The Phu Quoc is the first island city in Vietnam, and today electricity supply for the city implemented by the 110 kV undergrounded line, but electricity demand of the island is increased very rapidly so the very expensive 110 kV cable challenges overloaded risk. Therefore, the early completion of the 220kV Kien Binh – Phu Quoc transmission line should contribute in ensuring a long-term stable, safe and reliable electricity supply for power source, contributing to ensuring safe, continuous and reliable power supply for economic recovery, security and national defense […]
Owning the largest fleet of deck barges available for charter on the market today, Son Ha Marine Service, a barges rental company, offers the flexibility our customers need to secure the right barge services for their marine transport and construction projects. Our extensive fleet of inland barges and ocean barges includes deck barges, spud, and power spud barges, hopper barges, and shale barges. Our barge services include rental solutions to supply intermittent barge needs while removing the fleeting costs and compliance responsibility associated with barge ownership. Our cost-effective barge solutions allow our customers to focus on their projects and dedicate their capital to projects that benefit their business.