Location: Nghi Thiet commune, Nghi Loc district, Nghe An province
Scope of work:
• Piling and construction of 5,000 DWT, 50,000 DWT berths and approach bridges.
• Total volume: 10,000md PHC and SPP piles D600 & D800 (length 36-48m)
• Duaration time: From May 2017 to April 2018
Equipment used:
• 2700T barge with 200T crawler crane – 10T/6.2T pile hammer
• 2000T barge with 150T crawler crane – 10T/6.2T pile hammer
• 2000T barge with 120T crawler crane – 8T/6.2T pile hammer
• 250T jackup with 200T crawler crane – 10T/6.2T pile hammer