Location: Hoa Dong commune, Vinh Chau town, Soc Trang province.
Scope of work:
- Receive 22 WTGs components from the ship, load onto trucks, and transport to the yard for storage and preservation at Long An port
- Unload 22 WTGs components from trucks to the yard.
- Lift 22 WTGs components from the yard onto trucks and transport to the pier for delivery to barges or ships.
- Load 22 WTGs components from trucks onto barges transport or ships.
- From April 2021 to May 2022
Equipment used:
- Crane from 80T-500T
- Hydraulic railer 12 axle
- Lowbed trailer
- Extendable trailer 12 & 8 axle