Soc Trang 7 phase 1 nearshore wind project

Location:  Au Tho B Hamlet, Vinh Hai Commune, Vinh Chau Town, Soc Trang Province.
Scope of work: 

Construction foundation of PHC800/60-70m pile driving (from November 2020 to March, 2021)

Total weight: 4,000md
Equipment used:

1800 ton barge with 150 ton crawler crane – 10T/6.2T pile hammer