Sunpro Ben Tre wind power project

Location:  Binh Dai district, Ben Tre province

Scope of work: 

  • Receive 07 WTGs of Goldwind 4.5Mw components from the ship, load onto trucks, and transport to the yard for storage and preservation at Long An port.
  • Unload 07 WTGs components from trucks to the yard.
  • Lift 07 WTGs components from the yard onto trucks and transport to the pier for delivery to barges or ships.
  • Load 07 WTGs components from trucks onto barges transport or ships.
  • From July 2021 to May 2022

Equipment used:

  • Crane from 80T-500T
  • Hydraulic railer 12 axle
  • Lowbed trailer
  • Extendable trailer 12 & 8 axle