Son Ha MS completes logistics works for 4 wind farm projects at Long An International Port

Date: May 31, 2022

Son Ha MS has successfully completed all transportation, handling, and logistics works for four wind farm projects, including Hoa Dong 2 (Soc Trang), Thanh Phong (Ben Tre), Sunpro (Ben Tre), and Hoa Binh 2 (Bac Lieu), at Long An International Port.

Under the project scope, Son Ha MS handled a total of 61 sets of Goldwind, Vestas wind turbine components (WTGs), including 3.3MW and 4.5MW models. The scope covered receiving cargo from international vessels, unloading, yard storage and preservation, as well as lifting, transportation, and loading onto barges or vessels for delivery to project sites.

For specialized operations, Son Ha MS also executed the lifting of 13 nacelle units, each weighing up to 138 tons, requiring high precision and strict safety control.

The projects were carried out from April 2021 to May 2022, requiring seamless coordination across port operations, heavy transportation, and marine logistics.

To ensure safe and efficient execution, Son Ha MS deployed a comprehensive fleet of equipment, including cranes ranging from 80T to 500T, 12-axle hydraulic trailers, lowbed trailers, and extendable trailers (8 and 12 axles), supported by an experienced engineering and operations team.

The successful delivery of multiple projects at a single logistics hub demonstrates Son Ha MS’s strong capability in providing integrated solutions for wind turbine logistics, from port handling to final delivery.